Interlock Defeat /
Device Disable
Management System
v2.0
(Driver)
Accelerator Complex:
Driver
RIB
TR13
☰
Ops Apps Page
3DB
Webplan
Home
List of Defeats ▸
All
Active
Unacked
List of Disables ▸
All
Active
Unacked
Fill Out a Defeat
Fill Out a Disable
Add/Modify User
Add/Modify System
Login
Help
Implementation
Removal
Interlock Defeat
System(s) Affected:
Fire Alarm System
Interlock to be Defeated:
ARIEL Target Hall and Vesda detectors (09:095-001 and 002, 09:094-045)
Implementation:
Number:
Date:
2024-06-25
Time:
07:14:00
2024-335
Implemented By:
Chris Sooley
In Consultation With:
Status:
Removed
Estimated Duration:
8 hours
Reason for Defeat:
Construction work in ARIEL Target Hall.
Number of Yellow Tags:
1
Location of Defeat Tag(s):
FAS Panel
How Was Defeat Implemented?
Where is Defeat Located?:
F.A.S. Graphics panel.
Describe Alternate Protection:
Fire watch. People working in the area.
Fault Reports:
Work Permits:
A2024-05-27-1
Disables:
Interlock Defeat
Removal:
Number:
Date:
2024-06-25
Time:
15:15:00
2024-335
Removed by:
Travis Kurucz
Status:
Removed
Interlock Verification Method:
Devices rearmed and fas panel reset.
Number of Tags Removed:
1
Comments:
Brandon Humphries
David Bandiera
Elena Bylinskaia
Jason Wait
Sierra Dean
Robert Scheepmaker
Eric Chapman
Ryan Lovelidge
Riley Schick-Martin
Dale Nagra
Travis Kurucz
Chris Sooley
Kevin Lucow
Jas Uppal
Kathleen Genge
Gauhar Hayat
Frank Hosta
Ryan Anderson