Safety |
M9A Beam Blocker forced IN, IBOP 1814 pinned |
Implementation: | Number: |
2024-05-30 13:45:00 | 2024-281 |
Eric Chapman |
|
|
Removed |
Est. Duration: 52 weeks |
M9A BB control and readback signals connected incorrectly. No device status available on CSS. |
Successful pass of M9A BB SCBCD commissioning paperwork after being reconnected to CSS and air supply restored. |
3 |
DCR defeats board, IBOP pin 1814, locally at M9A BB air supply valve. |
M9A Beam Blocker air supply locked out by Mike Vogel, depressurizing air supply, driving beam blocker to IN limit. IBOP 1814 pinned to show M9 BB at IN limit on CSS. |
Visual confirmation Beam Blocker is in by Mike Vogel. |
OPS lock 118 |
Eric Chapman: 2024-06-01 15:20:24.522148
Disable tag added to M9 ignition key, already removed to lockout cabinet in DCR from previous disables for M9H and M9B.
Kevin Lucow: 2024-05-30 14:27:32.956369
Disable Tag added to Key 118 in MCR Lockout cabinet.