Services |
AL-ALCW Heat Exchanger Valves H-18 closed and D-17 throttled |
Implementation: | Number: |
2024-12-22 05:13:00 | 2024-582 |
Gauhar Hayat |
|
Jas Uppal |
Active |
Est. Duration: 16 weeks |
Reduced heat load, main magnet is off. |
Main magnet back on. |
3 |
Al-ALCW Ht. Ex. Valves H-18, D-17. MCR Defeat Board. |
SAB3 heat exchangers H-18 closed and D-17 throttled. |
Visially confirmed valve position at heat exchangers H-18 and D-17. |
|
|
|
|
|