Shielding |
BL1 Ignition key |
Implementation: | Number: |
2025-01-07 07:47:00 | 2025-7 |
David Bandiera |
|
|
Active |
Est. Duration: 16 weeks |
Annual 1A shielding block migration from Meson Hall to Parking Lot. |
Shielding restored to original configuration and verified by beamlines group. |
2 |
1) BL1 Ignition Key 2) DCR Defeats Board |
BL1 Ignition Key removed from slot above H panel and placed in OPS cabinet. |
Cannot enable BL1 safety devices from Safety Panel. Cyclotron is off for winter shutdown. |
|
|
C2025-01-07-1 |
|
|