Interlock Defeat /
Device Disable
Management System
v1.5
(Driver)
Accelerator Complex:
Driver
RIB
TR13
☰
Ops Apps Page
3DB
Webplan
Home
List of Defeats ▸
All
Active
Unacked
List of Disables ▸
All
Active
Unacked
Fill Out a Defeat
Fill Out a Disable
Add/Modify User
Add/Modify System
Login
Help
Implementation
Removal
Interlock Defeat
System(s) Affected:
Fire Alarm System
Interlock to be Defeated:
ARIEL North detectors
Implementation:
Number:
Date:
2024-01-16
Time:
10:45:00
2024-38
Implemented By:
Travis Kurucz
In Consultation With:
Elena Bylinskaia
Status:
Removed
Estimated Duration:
8 hours
Reason for Defeat:
Coring in tgt hall through to B1-08. Devices: 09:91-1-3,5-8,19; 09:92-1,2,11,15,18,19; 09:93-1,3-14,16,17,19,35; 09:94-42,45; 09:95-1,2,4; 09:98-1
Number of Yellow Tags:
1
Location of Defeat Tag(s):
How Was Defeat Implemented?
Where is Defeat Located?:
Devices disarmed from FAS graphics panel
Describe Alternate Protection:
Workers in area.
Fault Reports:
Work Permits:
Disables:
Interlock Defeat
Removal:
Number:
Date:
2024-01-16
Time:
10:45:00
2024-38
Removed by:
Jas Uppal
Status:
Removed
Interlock Verification Method:
Detectors enabled.
Number of Tags Removed:
1
Comments:
Travis Kurucz:
2024-01-16 10:42:34.717682
WP: A2024-01-15-1
Brandon Humphries
David Bandiera
Elena Bylinskaia
Jason Wait
Robert Scheepmaker
Eric Chapman
Ryan Lovelidge
Riley Schick-Martin
Dale Nagra
Travis Kurucz
Chris Sooley
Kevin Lucow
Jas Uppal
Kathleen Genge
Gauhar Hayat
Frank Hosta
Ryan Anderson