Interlock Defeat
System(s) Affected:
Fire Alarm System
Interlock to be Defeated:
ARIEL North detectors
Implementation:
Number:
Date:
2024-01-22
Time:
08:30:00
2024-44
Implemented By:
Chris Sooley
In Consultation With:
Dale Nagra, Ryan Lovelidge
Status:
Removed
Estimated Duration:
8 hours
Reason for Defeat:
Coring in tgt hall through to B1-08. Devices: 09:91-1-3,5-8,19; 09:92-1,2,11,15,18,19; 09:93-1,3-14,16,17,19,35; 09:94-42,45; 09:95-1,2,4; 09:98-1
Number of Yellow Tags:
1
Location of Defeat Tag(s):
FAS XL panel
How Was Defeat Implemented?
Where is Defeat Located?:
Devices disarmed from FAS graphics panel
Describe Alternate Protection:
Workers in area
Fault Reports:
Work Permits:
A2024-01-15-1
Disables:
Interlock Defeat
Removal:
Number:
Date:
2024-01-22
Time:
16:30:00
2024-44
Removed by:
Elena Bylinskaia
Status:
Removed
Interlock Verification Method:
Detectors re-armed. F.A.S. reset ok.
Number of Tags Removed:
1
Comments:
Elena Bylinskaia:
2024-01-22 16:30:57.329342
The Job reported to be completed for the day.
Brandon Humphries
David Bandiera
Elena Bylinskaia
Jason Wait
Robert Scheepmaker
Eric Chapman
Ryan Lovelidge
Riley Schick-Martin
Dale Nagra
Travis Kurucz
Chris Sooley
Kevin Lucow
Jas Uppal
Kathleen Genge
Gauhar Hayat
Frank Hosta
Ryan Anderson