Implementation
Removal
Interlock Defeat
System(s) Affected:
Fire Alarm System
Interlock to be Defeated:
ARIEL Target Hall and Vesda detectors (09-095-001 and 002, 09:094-045)
Implementation:
Number:
Date:
2024-06-24
Time:
07:33:00
2024-332
Implemented By:
Elena Bylinskaia
In Consultation With:
Elena Bylinskaia, Elena Bylinskaia
Status:
Removed
Estimated Duration:
8 hours
Reason for Defeat:
Construction work in ARIEL Target Hall.
Number of Yellow Tags:
1
Location of Defeat Tag(s):
n/a
How Was Defeat Implemented?
Where is Defeat Located?:
F.A.S. Graphics panel.
Describe Alternate Protection:
Fire watch. People working in the area.
Fault Reports:
Work Permits:
Disables:
Interlock Defeat
Removal:
Number:
Date:
2024-06-24
Time:
14:50:00
2024-332
Removed by:
Travis Kurucz
Status:
Removed
Interlock Verification Method:
Devices rearmed and FAS panel reset.
Number of Tags Removed:
1
Comments:
Brandon Humphries
David Bandiera
Elena Bylinskaia
Jason Wait
Sierra Dean
Robert Scheepmaker
Eric Chapman
Ryan Lovelidge
Riley Schick-Martin
Dale Nagra
Travis Kurucz
Chris Sooley
Kevin Lucow