Shielding |
Cyclotron Ignition Key and BL1 Ignition Key locked out |
Implementation: | Number: |
2024-04-24 16:00:00 | 2024-207 |
David Bandiera |
|
|
Active |
Est. Duration: 2 weeks |
Shielding blocks removed from SE corner of Cyclotron Vault Roof for BL1 Diagnostics cable pull. |
Shielding blocks restored on Vault Roof SE Corner and positioning verified |
3 |
1) DCR Defeat Board 2) Cyclotron Ignition Key 3) BL1 Ignition Key |
Cyclotron Ignition Key and BL1 Ignition Key locked out in Ops cabinet |
Cyclotron will not enable without Ignition Key inserted. Beam Inhibit Devices cannot be removed/energized. |
|
|
C2024-04-24-8 |
|
|