Optics |
M9 Q1, Q2, and B1 P/S |
Implementation: | Number: |
2012-10-25 09:15:00 | 2012-2 |
Micheal Donohoe |
|
|
Active |
Est. Duration: 104 weeks |
M9 blanked off and not operational |
M9 ready for operation |
2 |
1) MCR defeat board 2) Lockout box North MHB1 |
P/S's locked out. M9 Q1 panel 069, key #6830. M9 Q2 panel 56, key #6402. M9 B1 panel 56, key #8720. Keys in lockout box North MHB1. |
Devices inoperable. |
6830, 6402, 8720 |
|
2012-10-25-3 |
|
Micheal Donohoe: 2020-11-14 11:45:03.864181
Original paper disable #6691. Requested/approved/implemented by Elena Bylinskaia.
Defeat still valid, locks still applied, have been tagged as per Beamlines (B.G.). - KG 28-Jun-2016