Optics |
EHDT:Q6 Power Supply power cord |
Implementation: | Number: |
2021-04-26 13:30:00 | 2021-134 |
Riley Schick-Martin |
|
|
Active |
Est. Duration: 8 weeks |
Insufficient beam position protection at EHD:DUMP. Requested by Thomas Planche. |
Better beam position protection implemented. |
2 |
Lock at MAC-EHR-039 EHDT:Q6 PS, E-Linac defeat cork board |
EHDT:Q6 power supply at MAC-EHR-039 on E-Hall roof locked out at power cord. |
Attempted to turn on power supply, saw that it would not turn on. |
OPS #104 |
|
|
|
Brandon Humphries: 2021-04-26 14:45:30.645043
Paper disable written up at E-LINAC Disable #135.